Question
Download Solution PDFPriya and Rahul started a project together, and after 'k' days, Priya left and Rahul finished the remaining project in 8 days. The time taken by Rahul and Priya alone to complete the whole project are in the ratio 2:1 respectively. If Rahul can complete the entire project in 20 days, then calculate the value of 'k'.
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
Rahul's time to complete the project = 20 days
Ratio of Rahul : Priya = 2 : 1 → So Priya's time = 10 days
Rahul finishes remaining work in 8 days
Let k = number of days Priya worked with Rahul at the beginning
Work done is 1 (whole project)
Work rates:
Rahul’s 1 day work = 1/20
Priya’s 1 day work = 1/10
Together, in 1 day, they do:
(1/10 + 1/20) = (2 + 1)/20 = 3/20 of the work per day
Work done in first k days:
Work done together in k days =
k × 3/20 = 3k/20
Remaining work =
1 − 3k/20 = (20 − 3k)/20
Rahul finishes remaining work in 8 days:
Rahul’s 1-day work = 1/20
So in 8 days = 8/20 = 2/5
Now equate:
(20 − 3k)/20 = 2/5
Multiply both sides by 20:
20 − 3k = 8
⇒ 3k = 12
⇒ k = 4
Thus, the correct answer is 4 days.
Last updated on Jul 8, 2025
-> The IBPS PO Vacancy 2025 has been released for 5208 Probationary Officer Posts.
-> The Institute of Banking Personnel Selection (IBPS) has officially released the PO Notification 2025 on 30th June 2025.
-> As per the notice, the prelims examination is scheduled for 17th, 23rd, 24th August 2025. The Mains Exam is scheduled for 12th October 2025.
-> The IBPS PO online application dates is from 1st July 2025 to 21st July 2025.
-> The selection process for IBPS PO includes a Preliminary Exam, a Mains Exam, and an Interview.
-> The selected candidates will get a salary pay scale from Rs. 48480 to Rs. 85920.
-> Candidates must download and practice questions from the IBPS PO previous year's papers and IBPS PO mock tests for effective preparation/