Download Solution PDFWhich of the following is a weakness of bar chart?
This question was previously asked in
WBMSC Sub-Assistant Engineer (Civil) 05 Jun 2022 Official Paper
Answer (Detailed Solution Below)
Option 4 : All of the above
Free Tests
View all Free tests >
WBMSC SAE Full Test 1
1 K Users
100 Questions
200 Marks
120 Mins
Detailed Solution
Download Solution PDFConcept:
- A bar chart or bar graph is a chart or graph that presents categorical data with rectangular bars with heights or lengths proportional to the values that they represent.
- In order to show the bar chart for activities the length of the bar represent the time required for completion of that activity.
The main advantages of bar charts are
- Bar charts are easy to read and understand
- The clear relationship between size and value allows easy comparison.
The main disadvantages of bar charts are:
- It cannot show sufficient detail to enable the timely detection of schedule slippages.
- The spare time for the activities cannot be determined.
- The bar chart does not show the dependency relationships among activities
- It is essentially a manual graphical presentation.
- The schedule can not be updated.
- Progress of the project can not be determined by bar chart
- Bar graphs tend to be locked into a particular data set, making it hard to show multiple values or changes over time unless the chart is modified.
Last updated on Jun 14, 2025
-> Candidates can apply for the West Bengal Sub Assistant Engineer recruitment from June 18 to July 8.
-> A total of 125 vacancies are announced for WBMSC Sub Assistant Engineer Recruitment.
-> West Bengal Sub AE Notification 2025 has been released.
-> Candidates should refer to the West Bengal Sub Assistant Engineer Syllabus for their preparations.
-> Practice West Bengal Sub Assistant Engineer previous year papers.