To calculate the critical path in the given network diagram and find the critical duration, we need to determine the path with the longest duration from the start node to the finish node. The critical path is the one where any delay will affect the total duration of the project.
Analyzing the Paths:
1. Path A → C → F → J:
Total duration = 5 + 4 + 8 + 5 = 22
2. Path A → C → E → G → J:
Total duration = 5 + 4 + 7 + 10 + 5 = 31
3. Path A → C → E → H → I:
Total duration = 5 + 4 + 7 + 8 + 6 = 30
4. Path B → D → H → I:
Total duration = 8 + 9 + 8 + 6 = 31
Conclusion:
The critical path duration is 31 units.
Last updated on Jun 4, 2025
-> OSSC JE Preliminary Fiinal Answer Key 2025 has been released. Applicants can raise objections in OSSC JE answer key till 06 June 2025.
-> OSSC JE prelim Exam 2025 was held on 18th May 2025.(Advt. No. 1233/OSSC ).
-> The OSSC JE 2024 Notification was released for 759 vacancies through OSSC CTSRE 2024.
-> The selection is based on the written test. This is an excellent opportunity for candidates who want to get a job in the Engineering sector in the state of Odisha.
-> Candidates must refer to the OSSC JE Previous Year Papers to understand the type of questions in the examination.