The egg-shaped sewer is placed, such that:

This question was previously asked in
RRB JE CE 22 Apr 2025 Shift 1 CBT 2 Official Paper
View all RRB JE Papers >
  1. the velocity of flow is always lesser than the velocity of flow in hydraulically equivalent circular sewer
  2. the larger base has to support the weight of the upper smaller section
  3. the smaller base has to support the weight of the upper broader section
  4. the base and upper section has the same area and the middle section has large area

Answer (Detailed Solution Below)

Option 3 : the smaller base has to support the weight of the upper broader section
Free
General Science for All Railway Exams Mock Test
2.1 Lakh Users
20 Questions 20 Marks 15 Mins

Detailed Solution

Download Solution PDF

Explanation:

F1 Abhayraj.L 21-12-20 Savita D13

The egg-shaped sewer is designed for combined sewer systems, which carry both sanitary sewage and stormwater. It has a narrower bottom and wider top, and is placed with the smaller (narrow) end at the bottom for the following reasons:

  • Self-cleansing velocity: During dry weather (low flow), the narrow bottom ensures higher velocity to prevent sediment deposition.

  • High discharge capacity: During storms, the upper wider section accommodates large volumes of water.

  • The smaller base (narrower section) supports the broader upper portion of the sewer.

Additional InformationEgg-shaped Sewer

Shape and Design:

  • The sewer has a distinctive egg-like shape with a narrower bottom (smaller base) and a wider top (larger base).

Purpose:

  • Primarily used in combined sewer systems to handle both sanitary sewage and stormwater flows.

Flow Efficiency:

  • The design is intended to optimize flow conditions during varying discharge rates.

  • Self-cleansing velocity is achieved by the narrow bottom section, which promotes higher velocity during low flow conditions, preventing sedimentation.

Capacity:

  • The wider top section provides more capacity during high flow conditions, such as during heavy rainfall or storms, allowing the system to handle increased discharge.

Advantages:

  • Minimizes sediment deposition during low flow by maintaining sufficient flow velocity.

  • Increases discharge capacity in storm conditions due to the larger upper section.

  • Optimized for combined sewage systems by providing efficient flow at various conditions.

Latest RRB JE Updates

Last updated on Jun 7, 2025

-> RRB JE CBT 2 answer key 2025 for June 4 exam has been released at the official website.

-> Check Your Marks via RRB JE CBT 2 Rank Calculator 2025

-> RRB JE CBT 2 admit card 2025 has been released. 

-> RRB JE CBT 2 city intimation slip 2025 for June 4 exam has been released at the official website.

-> RRB JE CBT 2 Cancelled Shift Exam 2025 will be conducted on June 4, 2025 in offline mode. 

-> RRB JE CBT 2 Exam Analysis 2025 is Out, Candidates analysis their exam according to Shift 1 and 2 Questions and Answers.

-> The RRB JE Notification 2024 was released for 7951 vacancies for various posts of Junior Engineer, Depot Material Superintendent, Chemical & Metallurgical Assistant, Chemical Supervisor (Research) and Metallurgical Supervisor (Research). 

-> The selection process includes CBT 1, CBT 2, and Document Verification & Medical Test.

-> The candidates who will be selected will get an approximate salary range between Rs. 13,500 to Rs. 38,425.

-> Attempt RRB JE Free Current Affairs Mock Test here

-> Enhance your preparation with the RRB JE Previous Year Papers

Get Free Access Now
Hot Links: teen patti royal - 3 patti teen patti online teen patti king teen patti real teen patti mastar