The master production schedule represents the:

This question was previously asked in
RRB JE ME 22 Apr 2025 Shift 2 CBT 2 Official Paper
View all RRB JE Papers >
  1. starting time of component manufacturing
  2. financial requirements for the production
  3. starting and finishing time of different products
  4. finishing time of component manufacturing

Answer (Detailed Solution Below)

Option 3 : starting and finishing time of different products
Free
General Science for All Railway Exams Mock Test
2.1 Lakh Users
20 Questions 20 Marks 15 Mins

Detailed Solution

Download Solution PDF

Explanation:

Master Production Schedule (MPS):

  • The Master Production Schedule (MPS) is a critical component of production planning in manufacturing operations. It represents a detailed plan that specifies the starting and finishing times of different products. This schedule serves as a bridge between customer demand and the production system, ensuring that the right products are manufactured at the right time in the required quantities. The MPS is a key input for material requirements planning (MRP) and helps in achieving a balance between supply and demand.
  • The primary purpose of the MPS is to ensure that production aligns with customer demand while optimizing the use of available resources. It provides a clear roadmap for production activities, helping to avoid overproduction, underproduction, and stockouts. The MPS also ensures that production is carried out efficiently, minimizing waste and reducing costs.
  • The MPS is created based on customer orders, sales forecasts, and inventory levels. It is typically divided into time buckets, such as daily, weekly, or monthly intervals. The schedule specifies the quantities of each product to be produced in each time bucket, along with the starting and finishing times for production activities. The MPS is regularly updated to reflect changes in customer demand, production capacity, and inventory levels.

Key Features:

  • The MPS specifies the quantity of each product to be produced over a specific time period.
  • It defines the starting and finishing times for the production of each product, ensuring that deadlines are met.
  • The schedule takes into account factors such as available production capacity, inventory levels, and lead times.
  • It serves as a guideline for procurement, ensuring that raw materials and components are available when needed.

Advantages:

  • Helps in achieving a balance between supply and demand, reducing the risk of stockouts and overproduction.
  • Provides a clear roadmap for production activities, ensuring that deadlines are met.
  • Improves resource utilization by optimizing the use of available production capacity.
  • Facilitates better coordination between production, procurement, and sales functions.
Latest RRB JE Updates

Last updated on Jun 7, 2025

-> RRB JE CBT 2 answer key 2025 for June 4 exam has been released at the official website.

-> Check Your Marks via RRB JE CBT 2 Rank Calculator 2025

-> RRB JE CBT 2 admit card 2025 has been released. 

-> RRB JE CBT 2 city intimation slip 2025 for June 4 exam has been released at the official website.

-> RRB JE CBT 2 Cancelled Shift Exam 2025 will be conducted on June 4, 2025 in offline mode. 

-> RRB JE CBT 2 Exam Analysis 2025 is Out, Candidates analysis their exam according to Shift 1 and 2 Questions and Answers.

-> The RRB JE Notification 2024 was released for 7951 vacancies for various posts of Junior Engineer, Depot Material Superintendent, Chemical & Metallurgical Assistant, Chemical Supervisor (Research) and Metallurgical Supervisor (Research). 

-> The selection process includes CBT 1, CBT 2, and Document Verification & Medical Test.

-> The candidates who will be selected will get an approximate salary range between Rs. 13,500 to Rs. 38,425.

-> Attempt RRB JE Free Current Affairs Mock Test here

-> Enhance your preparation with the RRB JE Previous Year Papers

Get Free Access Now
Hot Links: teen patti apk teen patti joy apk teen patti circle teen patti royal